Building an ADU is an investment of time as well as money. Most projects take one to two years to complete. Typically, it takes homeowners one to three months to get started and assemble their team, then one to six months to develop plans, meet with the city, and submit the application. Depending on what permits are required, how many rounds of review are required and how quickly a homeowner and their project team can respond to comments, it will take one to three months to get permits. Construction usually takes six to twelve months.